Major projects
Gareth Turner has been involved in the construction and commissioning phases of a number of projects globally.
Dragon LNG
Over a three year duration was responsible for creating a test methodology involving both pneumatic and hydrostatic testing, oversaw the testing, pre-commissioning and commissioning phases.
Designed and performed the pre startup cooldown using liquid Nitrogen.
GATE LNG
Was responsible for the pipe testing and cleanliness operations during construction.
Engineered and performed pree-commissiong activities including drying and Nitrogen purging.
Designed and performed the pre start up cooldown using Liquid Nitrogen.
Isle Of Grain LNG
Designed and performed a number of pre start up cooldown activities.
RAPID LNG
Engineered a complete testing methodology for the projects including pneumatic and hydrostatic testing.
Carried out pre-commissioning activities including drying and Nitrogen purging.
Designed and engineered to pre start up cooldown system.